Five stages, each with defined deliverables and an indicative duration.

Stage Deliverables Typical duration
1. Requirement freeze Specification, ASIL allocation, standards list, interface definition 2–4 weeks
2. A-sample Functional prototype, bench validation, CAN matrix draft 10–14 weeks
3. B-sample Design for manufacturing revision, thermal validation, EMC pre-scan 12–16 weeks
4. DV / PV Design verification and product validation reports, EMC and environmental testing 14–20 weeks
5. SOP Series production, PPAP documentation, capacity ramp Per programme
  • Durations are indicative and depend on scope.
  • CAN matrices, safety documentation and test reports are exchanged under NDA.